E-Berkeley Management
Plan for FY 2002 and 2003
Approved 9/28/01
The E-Berkeley Management Plan is a guide to the various processes and timelines associated with the E-Berkeley Initiative for FY 2002 and 2003. The plan is intended to engage the Berkeley campus and the E-Berkeley Steering Committee in the various planning, budgeting and communication processes that are essential to the successful implementation of E-Berkeley.
The goal of the E-Berkeley initiative is to transform our community through
technology enabled learning, discovery, and engagement. The initiative provides
support for innovative strategies and experiments that will substantially improve
the university's ability to deliver effective and efficient services for students,
faculty, staff, alumni, and the general public.
Values underlying the E-Berkeley initiative are:
Objectives for the next two years include:
Planning:
During fall semester 2001,
the E-Berkeley Implementation Task Force through the E-Berkeley Program Office
will develop a multi-year project plan that encompasses both ongoing and new
E-Berkeley initiatives. The plan will include specific project deliverables,
timelines and budgets.
Also in the fall of 2001,
the E-Berkeley Steering Committee will review and modify the E-Berkeley vision
statement to ensure that it is consistent with the current initiatives and priorities.
The committee will also review the priorities and initiatives contained in the
detailed E-Berkeley project plan and make any necessary modifications.
During the 2001-2002 academic
year, a new teaching and learning initiative will be defined that will promote
the creation and dissemination of e-learning creative works of UC Berkeley faculty.
Standards and Guidelines:
During fall semester 2001,
campus review of E-Berkeley policies will continue, and information privacy/security
standards will be clarified and publicized. More detailed guidelines for the
E-Berkeley technical architecture will be defined during fall 2001 and spring
2002 semesters, in parallel with detailed planning for major E-Berkeley projects.
Project Management:
All FY2002 E-Berkeley projects
will be coordinated through the E-Berkeley Program Office. All projects will
have an approved budget, a detailed project plan and a set of benchmarks that
can be used to measure the success and outcomes of the projects. These benchmarks
will include specific action items, and also will include a review of the projects
for compliance with Berkeleys e-architecture guidelines and appropriate
security measures. The E-Berkeley Program Office will administer funding and
prepare status reports for review by the E-Berkeley Implementation Task Force
and the E-Berkeley Steering Committee. Each project will be assigned both a
technical and functional project lead by the project sponsor. The leads for
each project will work with the E-Berkeley Program Office to ensure that the
project proceeds according to schedule and within budget.
This process will be available to E-Berkeley projects not funded through the
E-Berkeley budget, but instead funded by the project sponsor. Project sponsors
are encouraged to take advantage of this process, since a major focus of the
Program Office is to improve coordination of E-Berkeley projects with other
campus IT initiatives.
The new project management process will be reviewed at each E-Berkeley project
manager meeting (every six weeks) to identify any problems with the project
management methodology and to improve coordination among the projects. A formal
written assessment of the project management process will be completed in January
2002.
FY2003 Budget Process:
In the fall of 2001 revisions
to the existing E-Berkeley budget process will be presented to the E-Berkeley
Steering Committee. This process will be based on lessons learned from the FY
2002 budget process. New elements of the FY2003 budget process could include:
an innovation fund to develop and nurture new E-Berkeley projects and initiatives;
a prioritization of infrastructure projects that are critical to the success
of E-Berkeley; and a clearer definition of what constitutes an E-Berkeley project.
Once approved by the E-Berkeley
Steering Committee, the process will be well publicized on the campus and will
provide advance information to facilitate the preparation of specific project
proposals.
Communication:
The communication plan approved
by the E-Berkeley Steering Committee will serve as the basis for communicating
with the Berkeley campus and external constituencies. Specific components of
the plan and their status are outlined below:
1. E-Berkeley Web Site (launched
4/01)
2. Branding of E-Berkeley (logo created 4/01)
3. Internal Campus Communication
a. Articles about E-Berkeley (on-going articles in the Berkeleyan, Daily Cal, other campus publications)
b. Campus/unit forums (to be developed)
c. Followup with units that submitted first year E-Berkeley proposals (letter sent 6/01)
d. Communicate revised budget request process for second year proposals (to be done)
a. Chancellor's video (completed)
b. Local media (to be developed)
c. National publications (to be developed)
Where possible, E-Berkeley communications will utilize existing communication
channels, rather than creating completely new approaches to communications.
Funding:
During fall semester 2001,
under the guidance of the E-Berkeley Steering Committee, the E-Berkeley Program
Office will begin to pursue alternate sources of funding, through national foundations
and corporate partners and other potential donors, for specific initiatives
as well as seed funds for innovative projects. The E-Berkeley Program Office
will continue to develop relationships with our corporate partners, with a goal
toward utilizing our partners professional expertise to help us in areas
such as external communications and project planning.
Education and Training: Ongoing education for the campus at all levels must
continue. The E-Berkeley Program Office will partner with Human Resources and
with Information Systems and Technology to develop a coordinated approach to
training for the campus.
Measurement:
This Management Plan will be reviewed by the E-Berkeley Steering Committee and updated at least once a year. Individual projects will be measured by metrics being devised by the Program Management Office and Information Systems and Technology. Current plans include assessing real versus estimated project costs, real versus estimated time to complete each project, user satisfaction, and service usage trends.
Prepared
by:
Barbara Morgan, IST, for the E-Berkeley Steering Committee (barbm@uclink)
Jon Conhaim, E-Berkeley Program Management Office (conhaim@uclink)